Queue Point Residential Project: Mazaya on Schedule


22/06/2009 00:00 AST

Kuwait-based Al Mazaya Holding is still sticking to the payment collection process as stipulated in the sales and purchase agreement for its Queue Point residential project at Liwan in Dubailand despite the project being delayed by eight months, said a senior company executive.

“The payment collection process is running according to the schedule agreed upon in the contracts. Queue Point was scheduled for completion by September 2009 and is now delayed until May 2010,” Salwa Malhas, Executive Vice-President of Al Mazaya Holding, told Emirates Business.

Most of the real estate developers in Dubai have shifted to construction milestone payment plans after their projects got delayed.

Al Mazaya Chief Executive Officer Khalid Esbaitah said: “Delays in the handover of land, completion of infrastructure within the Liwan master development and hiring the right contractors for the project are the main reasons for the delay in the completion of Queue Point. However, now all the obstacles have been removed and we are on track to hand over the development by May 2010.”

A Tatweer spokesperson said: “We are only responsible for the development of infrastructure at Liwan City; the infrastructure works are progressing on schedule. All land plots have been handed over to the investors. We confirm all infrastructure is in line with the required development plans by the investors and developers.”

Last week some Queue Point investors told this newspaper that work had begun on only parts of the project, while most of the site remained undeveloped. “Construction has started only on some buildings but a lot of the project is yet to be developed,” said one investor who wished to remain anonymous. “In some places even the fencing has not been put in place. But the developer is constantly asking for payments. When we contacted the developer, it said we had a fixed payment plan and the payments had to be made. We have started paying, but we have been on the site and not a grain of sand has been moved.”

But Malhas said construction had started on all the buildings in the Queue Point project. “The payment collection process is running according to the schedule agreed upon in the contracts,” she said. “Usually the percentage of completion of a project is not measured by the completion on site, because there are many steps that need to take place before work commences on the site such as design, getting permits and mobilisation. These steps are considered part of the development process and must also be taken into account when considering the percentage completion of a project.

For more on this:

http://www.rootsland.com/real-estate/queue-point-residential-project-mazaya-on-schedule/

www.rootsland.com
Al-Mazaya Holding Co. - MAZAYA
2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | News Archive
Most Viewed Companies
Ticker Price Volume
YAMAMAHSTEEL 40.03 5,562,033
SABIC 81.59 4,712,483
RIBL 11.07 377,645
SIPCHEM 13.98 196,375
ALMARAI 53.75 192,894
EEC 27.71 418,051
SACCO 63.75 507,469
Recent News

Dallah Health announces signing of contract costing SAR 334 million
Dallah Healthcare Holding Company announces the signing of a contract for mechanical, electrical work and plumbing of phase one for Dallah Hospital, Namar, southwest of Riyadh on 24/05/2015G. (corres

Saudi Cement announces cash dividends for 1st Half 2016
The Board of Directors of Saudi Cement Company has resolved during its meeting held on 24/05/2016 (17/08/1437), to distribute interim dividends to the shareholders for the period first half of 2016 a

Batelco quits Malta GO stake deal talks
Bahrain Telecommunications Co (Batelco) is no longer in talks to buy Maltese telecoms company GO, the Bahraini firm said on Tuesday.

Last week, Batelco announced it had submitted a bid for

NBK - Egypt reports $20.96m Q1 profit
National Bank of Kuwait-Egypt (NBK-E) reported net profits of EGP186.6 million ($20.96 million) for the first quarter of 2016 compared with EGP126.3 million for the same period in 2015, growing at 47

Dubai Holding unveils $272m waterfront development
Dubai Holding, a leading investment holding company, has announced the launch of its new waterfront destination, 'Marasi Business Bay,' to be developed along the creek within Business Bay destination

GulfBase GCC Index
Search By
  • Company Symbol
  • Company Name
  • Mutual Fund Name
  • News Content
Send this page to a friend

Poll

Looking ahead, what change you are more likely to make in investing in your domestic stock market?