Queue Point Residential Project: Mazaya on Schedule


22/06/2009 00:00 AST  www.rootsland.com

Kuwait-based Al Mazaya Holding is still sticking to the payment collection process as stipulated in the sales and purchase agreement for its Queue Point residential project at Liwan in Dubailand despite the project being delayed by eight months, said a senior company executive.

“The payment collection process is running according to the schedule agreed upon in the contracts. Queue Point was scheduled for completion by September 2009 and is now delayed until May 2010,” Salwa Malhas, Executive Vice-President of Al Mazaya Holding, told Emirates Business.

Most of the real estate developers in Dubai have shifted to construction milestone payment plans after their projects got delayed.

Al Mazaya Chief Executive Officer Khalid Esbaitah said: “Delays in the handover of land, completion of infrastructure within the Liwan master development and hiring the right contractors for the project are the main reasons for the delay in the completion of Queue Point. However, now all the obstacles have been removed and we are on track to hand over the development by May 2010.”

A Tatweer spokesperson said: “We are only responsible for the development of infrastructure at Liwan City; the infrastructure works are progressing on schedule. All land plots have been handed over to the investors. We confirm all infrastructure is in line with the required development plans by the investors and developers.”

Last week some Queue Point investors told this newspaper that work had begun on only parts of the project, while most of the site remained undeveloped. “Construction has started only on some buildings but a lot of the project is yet to be developed,” said one investor who wished to remain anonymous. “In some places even the fencing has not been put in place. But the developer is constantly asking for payments. When we contacted the developer, it said we had a fixed payment plan and the payments had to be made. We have started paying, but we have been on the site and not a grain of sand has been moved.”

But Malhas said construction had started on all the buildings in the Queue Point project. “The payment collection process is running according to the schedule agreed upon in the contracts,” she said. “Usually the percentage of completion of a project is not measured by the completion on site, because there are many steps that need to take place before work commences on the site such as design, getting permits and mobilisation. These steps are considered part of the development process and must also be taken into account when considering the percentage completion of a project.

For more on this:

http://www.rootsland.com/real-estate/queue-point-residential-project-mazaya-on-schedule/

Al-Mazaya Holding Co. - MAZAYA
2014 | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | 2007 | News Archive

JAN | FEB | MAR | APR | MAY | JUN | JUL
Most Viewed Companies
Ticker Price Volume
EEC 86.96 7,884,595
ARTC 4.23 192,972,723
RIBL 18.36 3,745,755
EMAAR 9.72 9,270,309
MMG 12.55
SECO 16.25 5,907,674
HAMMADIINVEST 49.2 157,360
Recent News

Bahrain Duty Free relaunches upgraded Shop & Collect Facility
Bahrain Duty Free have just relaunched an upgraded Shop & Collect facility for its customers at Bahrain International Airport. The upgraded system has reduced substantially the time needed to process

SAUDI STOCKS HIT 6-YEAR HIGH;
?Saudi? Arabia's bourse jumped today after the Capital Market Authority said it would open the stock market to direct investment by foreign financial institutions in the first half of 2015, news agen

Kingdom Holding’s net profit surges 16.8% in Q2
Kingdom Holding Company (KHC), chaired by Prince Alwaleed Bin Talal, registered a SR211.7 million net income in the second quarter ended June 30, 2014, an increase of 16.8 percent compared to SR181.2

Muscat index down marginally; Bank Nizwa gains the most
MSM 30 index ended on a flat note at 7182.02 points, down by 0.09 per cent. MSM Shariah Index also declined marginally by 0.08 per cent at 1069.17 points.

Global Financial Investment was

Rolta in Sadara engineering project
Rolta has been awarded an additional scope of work by Sadara Chemical Company (Sadara) to implement a comprehensive engineering information system within Sadara's Jubail integrated chemical complex.

GulfBase GCC Index
Search By
  • Company Symbol
  • Company Name
  • Mutual Fund Name
  • News Content
Send this page to a friend

Poll

Which of the following do you think is the best long-term investment?